Land and Approvals
Land secured before spend
Each project needs host land and statutory approvals that hold up to lenders. We run options, planning and heritage in parallel from Gate 2.
Inside the scope

What’s included
Land options
Planning approval
Heritage and native title
Easements and mortgagee consent
Native vegetation and environment
Community engagement
Specs
Option term
5 to 7 years
Lease term
30 to 35 years
Land gate
6 to 12 months
Approvals gate
12 to 24 months
Option cover
90% of layout
Wind approvals
Up to 30 months
Evidence
Land and approvals evidence that stands up at financial close, from option to planning decision.
Of the layout area under option at Gate 3
Neighbours contacted before wind layout is fixed
Months, longest approvals window (wind)
How We Work
Five steps from site screening to planning approval

FAQ
Common questions.
What do land options cover?
Five to seven year options over the layout area, converting to 30 to 35 year leases, with easements and mortgagee consent for lenders.
Which approvals apply?
In SA, the PDI Act 2016 and the Planning and Design Code. In Victoria, the Planning and Environment Act 1987 and the Development Facilitation Program.
How is heritage handled?
Surveys with Traditional Owner representatives, avoidance first, and agreements or ILUAs before Gate 4 exit.
Who is contacted first?
Neighbours, in person, before layout is fixed: within 2 km of wind turbines and 1 km of solar and battery.