Financial close, construction, then handover.

Saltbush acts as development and construction manager for the owner-operator, under lump-sum, date-certain EPC contracts based on AS 4902.

Two EPC contractors sit on early works agreements before one is selected. Long-lead plant is reserved before financial close, and AEMO hold points are tied to payment.

Discuss a Project
Contracts that fix price and date.

Lump-sum, date-certain EPC contracts. Two contractors on early works agreements until one is selected, with a preferred-bidder price at Gate 6.

Hold points tied to payment.

AEMO commissioning hold points are tied to payment, and an independent engineer reports to lenders. Practical completion is evidenced.

A handover pack, not a handshake.

At Gate 7 the owner-operator receives the handover pack: as-built records, AEMO commissioning sign-off and practical completion evidence.

Delivery Principles

Evidence at every gate, so the owner-operator takes on a project that is built, tested and documented.

Evidence at every gate, so the owner-operator takes on a project that is built, tested and documented.

01

Fixed price

Lump-sum, date-certain EPC contracts.

02

Early works

Two EPC contractors compared before one is selected.

03

Long-lead plant

Transformers, switchgear, batteries and turbines reserved early.

04

Independent engineer

Reviews design and construction for lenders.

05

Hold points

AEMO commissioning steps tied to payment milestones.

06

Handover pack

Records and sign-offs for the owner-operator.

FAQ

Common questions.

Does Saltbush own the project after construction?

No. We develop, build under management, then sell the project company to an owner-operator.

What does Saltbush manage during construction?

Procurement, the EPC contract, programme, safety and quality, for a construction management fee of 0.75% of capital cost.

How long does construction take?

About 15 to 20 months for solar and battery, and 24 to 30 months for wind (Gate 7).

What does the owner-operator receive?

A handover pack with practical completion evidence and AEMO commissioning sign-off.