From first enquiry to connection agreement.
We take each project from a connection enquiry to an executed agreement and AEMO-accepted performance standards under NER Chapter 5.
Eighteen to thirty-six months, starting at Gate 2 and running in parallel with land and approvals. Network studies and model acceptance set the pace.


What We Handle
Connection sits on the critical path.
Most delay sits in network studies and model acceptance, not construction. We start the enquiry at Gate 2, before approvals spend.
Each site is ranked on hosting capacity, fault level and system strength, so one connection schedule drives the project.
Connection enquiry
Hosting capacity and fault level tested with the network provider at Gate 2, before approvals money is spent.
Application and studies
Connection application and network studies with ElectraNet, SA Power Networks, AusNet Services or Powercor.
Performance standards
Generator performance standards proposed, negotiated and accepted by AEMO and the network provider.
R1 and R2 models
Plant models built and submitted for assessment, with AEMO acceptance required before Gate 5 exit.
System strength
System strength and fault level assessed early, with network works or plant design changes agreed in advance.
Connection agreement
An executed connection agreement and agreed network works, which are the evidence for Gate 5.

FAQ
Common questions.
Who do you deal with?
ElectraNet and SA Power Networks in South Australia, AusNet Services and Powercor in Victoria, and AEMO for registration and assessment.
How long does connection take?
About 18 to 36 months. It starts at Gate 2 and needs an executed agreement before Gate 5 exit.
What are R1 and R2 models?
Plant models submitted to AEMO and the network provider to assess performance standards and system strength.
What if system strength is short?
We test options early: network works or plant design changes, agreed with the network provider before financial close.