Technical Note

How we test a site for connection before we pay for approvals

24.11.2026

/

Posted by

Chief Development Officer

Technical Note

We test every site for grid connection at feasibility, before we pay for planning approvals. Approvals take 12 to 24 months, and a site that cannot connect at a reasonable cost is not worth approving.

The connection enquiry

At Gate 2 we lodge a connection enquiry with the relevant network service provider, such as ElectraNet in South Australia or AusNet Services in western Victoria. The reply gives preliminary network advice on where the project could connect and what network works may be required.

The advice goes into the feasibility report with concept design, P50 and P90 yield, a capex range, an indicative connection route and cost, and a constraint register. Connection cost then sits beside land and approvals risk from the start, not at the end.

What we check

We look at hosting capacity at the proposed connection point, the fault level, and system strength, which determines whether inverter-based plant can meet its generator performance standards without extra equipment. Each can change cost or layout, and each is recorded before we commit to approvals spending.

Ranking sites

We rank sites on connection evidence alongside land and resource. A site with a clear connection route moves up the pipeline; one with weak network evidence waits, or stops at Gate 2 by Investment Committee decision.

What this does not settle

A connection enquiry is not a connection agreement. An executed agreement, AEMO-accepted performance standards and agreed network works are Gate 5 evidence, and connection takes 18 to 36 months. Enquiry advice can change as the network and other applicants change, so we revisit it.